For an autumn/winter collection, a brand should usually start manufacturing work four to six months before the launch date, and earlier still if the range includes outerwear. At NO FUGAZI sampling takes about 2 to 3 weeks, and bulk production can take from 10 working days after the sample is approved, plus shipping. Winter garments usually need more than that fastest case: heavyweight fleece and loopback often need fabric knitted and dyed for the order, and puffers carry more operations and more fit checks than a tee. Work backwards from launch day, and leave a buffer for one revision round.
In this article
- Why autumn/winter takes longer than summer
- The countdown from launch day
- Start month to launch month
- Design and the brief
- Fabric is the first long pole
- Patterns and the first sample
- Reviewing a winter sample properly
- Bulk production and quality control
- Freight and the launch buffer
- Outerwear needs its own clock
- If you are already late
- Autumn/winter at NO FUGAZI
Why autumn/winter takes longer than summer
A summer range is mostly jersey: t-shirts, shorts, light layers. Jersey is quick to source, quick to cut, and forgiving to sew. An autumn/winter range is built from heavier cloth and more complicated garments, and almost every difference adds time somewhere.
| What changes in winter | Where the time goes |
|---|---|
| Heavier fabric, 350 GSM and up | Heavyweight loopback and brushed fleece in a custom colour are usually knitted and dyed for the order before anything is cut |
| Brushed fleece | An extra finishing step after knitting, and the nap has to be checked for consistency across the batch |
| Outerwear | Shell, lining, fill or padding, zips and trims all have to arrive before cutting starts, and the sewing runs to more operations |
| Layered fits | A hoodie or jacket meant to be worn over other layers needs its proportions judged on a body, which makes the sample review matter more |
| Garment dye and washes | A separate process after sewing, with its own drying and finishing time |
None of this makes winter production difficult. It makes it longer, and it makes late decisions more expensive in time, because a change to the fabric after it has been ordered is a change to the slowest part of the job.
The countdown from launch day
The cleanest way to plan is backwards. Fix the week you want product in customers' hands, then subtract each stage. The table below is a planning template for a first autumn/winter run of hoodies, sweatpants or tracksuits. For a first collection, plan with a buffer rather than the fastest case, because there is no previous sample to build on.
| Weeks before launch | What should be happening | Who drives it |
|---|---|---|
| 24 to 20 | Range decided, references gathered, garment list and quantities settled | You |
| 20 to 18 | Brief sent, quote and specification agreed, fabric choice confirmed | Both |
| 18 to 15 | Pattern drafted and first sample made, about 2 to 3 weeks | Manufacturer |
| 15 to 14 | Sample reviewed on a body, feedback written down in one list | You |
| 14 to 11 | Revision round if needed, then sample approved | Both |
| 11 to 3 | Bulk production and quality control: from 10 working days for a straightforward run; the rest of this window is buffer for heavier fabric, custom dyeing, outerwear and the production queue | Manufacturer |
| 3 to 1 | Freight, customs clearance and receiving stock | Freight |
| Final week | Buffer: checking the delivery, packing the first orders | You |
Read it as a template, not a promise. Production queues, quantity and the complexity of the design all move the manufacturing ranges, and the shipping method moves the freight line. What the table does show is that the decision stages at the top are where most founders lose the weeks they later try to recover at the bottom.
Start month to launch month
The same countdown, turned into months. It assumes a first run of hoodies, sweatpants or tracksuits with one revision round, and a bulk window that leaves room for heavier fabric, custom dyeing and the production queue rather than the fastest case. Add four to six weeks to every row if the range includes a puffer or another jacket.
| Product in customers' hands by | Send your brief by | Approve the sample by |
|---|---|---|
| Early September | Late March to early April | Early June |
| Early October | Late April to early May | Early July |
| Early November | Late May to early June | Early August |
| Early December | Late June to early July | Early September |
A brand selling direct to its own customers can work to these dates. A brand selling into shops works to the buyers' calendar instead, which sits months earlier, because stores commit to autumn/winter ranges well before the season.
Design and the brief
The first stage is the one nobody times. Before a pattern can be cut, somebody has to decide what each garment actually is: its fit, its weight, its colour, where the branding sits and how it is applied.
You do not need a tech pack to start. A sketch, a moodboard, photos of garments you like, or a garment you already own is a normal first brief, and the technical side gets drafted from that. What you do need is decisions. For a winter range the ones that matter most are:
- Fabric weight. A 320 to 400 GSM French terry hoodie is a three-season garment. 400 GSM and above, or brushed fleece, is a winter garment. Pick deliberately, because weight decides how the fit reads.
- Colour. A stock colour is quicker. A custom colour means a dye batch, which is often the longest single wait in a winter job.
- Fit intention. Will it be worn over a t-shirt, or over a hoodie? A layering piece needs more room through the chest and arm.
- Decoration. Embroidery sits well on heavy terry and fleece. Fine print detail struggles on a brushed surface.
If those four are settled before the brief goes out, the rest of the countdown has a chance of holding.
Fabric is the first long pole
In winter production the fabric decides the calendar more than the sewing does. A lightweight jersey in a stock colour can be on the cutting table quickly. A heavyweight loopback in a custom shade has to be knitted, dyed, finished and checked before a single panel is cut.
Three things push fabric lead time out, and all three are common in autumn/winter ranges:
- Custom colour. Every colourway in a custom shade is its own dye batch, and shade has to be approved before bulk dyeing.
- Brushing. Fleece is French terry with the inside loops brushed open, which is an extra pass through a machine after knitting.
- Matching trims. Rib for cuffs and hems has to match the body colour, and drawcords, zips and labels have to be sourced to suit.
The practical answer is to lock the fabric early, ideally at the brief stage, and to keep the number of custom colourways small for a first winter run. If you are choosing between French terry and fleece, our side-by-side comparison of French terry and fleece sets out the trade-offs.
Patterns and the first sample
Once the specification is agreed, the pattern is drafted for your fit and the first sample is cut and sewn. At NO FUGAZI that takes about 2 to 3 weeks. The sample is made in the real fabric where possible, because a heavyweight garment hangs completely differently from a lighter stand-in, and judging a winter fit on the wrong weight teaches you nothing.
The sample is where the expensive mistakes are caught cheaply. Sleeve length, hood depth, rib tension, the drop of a boxy shoulder and the weight of a pocket all show up on a real body in a way they never do in a drawing. Treat the sample as the most important single deliverable in the whole countdown, not as a formality before bulk.
If you are making several garments, sample the most complicated one first. In a winter range that is usually the outerwear, then the hoodie, then the bottoms.
Reviewing a winter sample properly
A winter sample needs a slightly different review from a summer one, because it is meant to be worn in layers and in the cold. Put it on, over what it will actually be worn over, and check:
- Whether the chest and arm still sit right over a hoodie or a heavy tee.
- Whether the cuffs and hem rib hold their shape after you have pushed the sleeves up and pulled them down a few times.
- Whether the hood stands or flops, and whether it covers the head with a cap underneath.
- Whether zips run cleanly through the full length on outerwear, and whether pockets sit where hands actually go.
- How the garment feels after a wash, if the fabric is not already pre-shrunk. Ask about residual shrinkage before you approve.
Write every change in one list and send it at once. A revision round costs roughly another sampling cycle, so two half-lists sent a week apart can quietly cost you a fortnight. One revision round is normal and is built into the template above. A second round is where autumn/winter launches start to slip into winter.
Bulk production and quality control
Bulk starts once the sample is approved. At NO FUGAZI it can take from 10 working days for a straightforward run, but winter ranges usually need longer, for the fabric reasons above and because heavy garments simply take longer to sew, press and finish. Garment dyes and washes add their own process after sewing.
Quality control runs through bulk rather than at the end of it: fabric inspection before cutting, checks during sewing, an inspection after production, and a final review before shipment. The approved sample is the standard the bulk is measured against, which is another reason to approve only a sample you are genuinely happy with.
The bulk window is also when you can work in parallel. Use the approved sample to shoot product photography and campaign content, write your product pages, and open pre-orders if that suits your launch. Founders who wait for stock to arrive before shooting add weeks to the end of the countdown that did not need to be there.
Freight and the launch buffer
Shipping is the last stage, and it is the one that depends least on the manufacturer. Air freight is faster and suits a small first run. Sea freight costs less per unit on larger volumes but adds weeks. Either way, allow time for customs clearance and for checking the delivery when it lands.
Freight lanes and carriers also get busier in the run-up to the main retail season, which is exactly when autumn/winter stock is moving. Build the buffer into the plan rather than hoping for a quiet week.
The final buffer is for you: counting and checking the delivery, steaming anything that needs it, and packing the first orders. A week is modest. A launch date with no buffer at all is a date that will move.
Outerwear needs its own clock
If the range includes a puffer, a bomber or a varsity jacket, plan that garment separately and start it earlier than the rest. Outerwear has more components and more operations: a shell fabric, a lining, insulation or padding, zips, snaps, rib and labels, and construction choices such as how the fill is quilted or baffled. Every component has to be sourced before cutting begins, and the fit has to be judged over the layers it will be worn on top of.
A sensible rule for a first winter collection is to add several weeks to the outerwear line of the countdown and to sample it first. If the jacket slips, you can still launch the hoodies and bottoms on time and drop the jacket a few weeks later, which is often a better story than delaying everything. Our pages on custom puffer jackets and custom hoodies cover how each one is built.
If you are already late
If the countdown says you should have started a month ago, the launch is not lost, but something has to give. The levers that save the most time, roughly in order:
- Choose stock colours over custom ones. Removing a dye batch takes the longest single wait out of a winter job.
- Move the outerwear to a second drop. Launch the hoodies and bottoms on time, and release the jacket a few weeks later.
- Cut the number of styles. One strong style sampled properly beats three rushed ones.
- Make decisions in days, not weeks. Review the sample the day it arrives and send one complete list of changes.
- Ship by air. For a small first run the faster transit can be worth more than the freight saving.
- Open pre-orders on the approved sample. Your launch date and your delivery date do not have to be the same day.
The one lever not on the list is skipping the sample. On a winter garment the sample is where fit, weight and shrinkage problems are caught, and a bulk run made without one is the most expensive way to lose time.
Autumn/winter at NO FUGAZI
We make autumn/winter ranges to order from 50 pieces per garment type: heavyweight hoodies and sweatshirts in loopback French terry or brushed fleece, sweatpants and tracksuits, and outerwear including puffers, bombers and varsity jackets. You do not need a tech pack. Send a sketch, a moodboard, photos or a garment you like, and we develop the pattern and the sample from that.
Sampling takes about 2 to 3 weeks, and bulk production can take from 10 working days after you approve the sample, with more time for heavier, custom-dyed or outerwear runs, plus shipping. Sampling is not charged as a separate line when you commit to the bulk run with a deposit. Sampling slots can book up ahead of busy periods, so the earlier you send a brief, the more of the countdown above you keep. You can see the full sequence on how our process works, or message us on WhatsApp with your launch date and we will tell you whether it is realistic.
Questions
How many months before launch should I start an autumn/winter collection?
Four to six months before launch is a realistic starting point for a first autumn/winter run of hoodies, sweatpants and tracksuits. Add several more weeks if the range includes outerwear such as puffers or bombers. Sampling takes about 2 to 3 weeks at NO FUGAZI and bulk can take from 10 working days after sample approval, with more time for heavier or more complex runs, but the decision stages before sampling and the revision round after it usually take longer than founders expect.
Why do winter garments take longer to manufacture?
Winter garments use heavier fabric and more components. Heavyweight loopback or brushed fleece in a custom colour is usually knitted and dyed for the order before cutting, brushing adds a finishing step, and outerwear needs a shell, lining, fill and trims sourced before production starts. Heavy garments also take longer to sew, press and finish, so winter bulk usually takes longer than the fastest 10-working-day case.
Can I shoot my campaign before the stock arrives?
Yes. Once the sample is approved it represents the finished garment, so you can photograph it, build your product pages and open pre-orders while bulk production runs. Doing this in parallel removes weeks from the end of the countdown. Only approve a sample you are happy to put in front of customers, because the bulk is made to match it.
What should I decide before I send an autumn/winter brief?
Decide the fabric weight, the colour, how the garment will be layered and how it will be decorated. Weight sets how the fit reads, a custom colour adds a dye batch, layering decides how much room the chest and arms need, and decoration has to suit the fabric surface. A tech pack is not required: a sketch, photos or a reference garment is enough to start.
Should I launch outerwear at the same time as hoodies?
Plan outerwear on its own, longer timeline and sample it first. Jackets have more components and operations, so they are the garment most likely to slip. If the jacket runs late, launching the hoodies and bottoms on time and dropping the jacket a few weeks later often works better than delaying the whole collection.
How many sample revisions should I allow for?
Plan for one revision round. Each round costs roughly another sampling cycle, so the countdown should assume one and treat a second as the point where an autumn launch starts slipping. Sending every change in a single written list, after trying the sample on over the layers it will be worn with, is the most reliable way to stay at one round.
Related reading
- How long does it take to start a clothing brand? – the full timeline for any first run, season aside.
- Streetwear fabric guide – GSM, French terry, fleece and jersey, and which suits which garment.
- What GSM should a hoodie be? – choosing weight for a three-season or a winter hoodie.
- Minimum order quantity explained – how the 50-piece minimum works across sizes and colourways.